A data centre can be ready before the grid can supply its full requested capacity. Where the network operator offers flexible connection terms, a site may be able to start sooner by reducing grid import during defined periods.

The engineering question is whether the available equipment can deliver the reduction reliably under the proposed conditions.

Define the flexibility requirement

EPRI’s Flex MOSAIC framework provides a common language for large-load flexibility. It describes requirements in terms of notice, activation duration and annual utilisation. Its evaluation approach considers workloads, on-site generation, storage and cooling. [1, 2]

The same 5 MW reduction can require very different equipment if it lasts for 30 minutes or six hours. Annual event frequency and recovery between events also matter.

Check the power and energy together

Consider a 20 MW data centre with a 15 MW import limit during a four-hour event. The site must reduce net grid demand by 5 MW, equivalent to 20 MWh over that event. A battery alone needs sufficient discharge power, usable energy and time to recharge.

Approved load reduction and permitted on-site generation can reduce the battery requirement. Start time, sustained output, fuel and emissions limits, and operating costs must be checked for each resource.

Try the GridPass flexibility calculator

Our free independent screening calculator compares three resource types against a proposed import limit. Enter site demand, event notice, duration, frequency, recovery time and resource limits. The tool estimates sustained demand reduction, the remaining grid import, battery recharge time and variable operating cost.

The calculator is a first-pass model, not an official Flex MOSAIC classification or a network connection approval. It uses constant demand and repeated events. GridPass can refine the model using site meter data, contractual terms and equipment specifications.

For a real project, the next step is to assess the local connection offer and develop a site-specific design and acceptance test plan.

Try the free flexibility calculator

Sources

  1. EPRI — Flex MOSAIC framework and evaluation tool
  2. EPRI — DCFlex deliverables, including the October 2026 framework paper
  3. Photograph: Carl Lender, Datacenter Server Racks
  4. Photo licence: Creative Commons Attribution 2.0
← All GridPass articles